How to show missed deadline indicator?

C

Catherine

I have tasks that have deadlines, yet when the actual date is beyond the
deadline, the "missed deadline" indicator does not show. How do I get the
indicator to show? Thank you.
 
J

JulieS

Hi Catherine,

If the task has an actual finish date, the icon that appears in the
indicator column is the checkmark showing the task is complete. I don't
believe you can change to show the missed deadline indicator instead of the
checkmark.
You could use one of the spare Flag fields with a custom formula:
for example:

IIf([Actual Finish]>[Deadline],Yes,No)

and then set a graphical indicator to display instead of the Yes, No.

Hope this helps. Please let us know how you get along.