Thanks Mike, I am using 2002 Pro. What we need is to show a Summary Progress
bar in a gant. Can show in normal view, Does not show when data is grouped?
Tks, CWW
When you apply grouping, you can't change the summary bars to show progress. However, you can insert the %Complete column which gives you the
data.