L
lbreysse
Hello,
I'm using MS Project Pro 2003, non enterprise version.
We are planning projets by allocating resources up to 80% (time
available for projects, excluding all organizational tasks).
We track efforts (with Actual work and Remaining work) and want a
schedule reflecting the reality.
For understaffing (less efforts produced than planned), updating
actual+remaining work, and rescheduling the planning gives good
results.
For overstaffing (more efforts produced than planned, ex: the engineer
worked 100% of his time on the task), we have to update the Actual work
in the 'Task usage' view to see the planned assignment be updated with
real efforts spent over the week. If not, we do not see the benefits of
a work advance due to an overstaffing.
Here is the problem:
Task A ends Week 1 : Actual work = 3 days
Task B follows task A: Actual work = 2 days
1/ When I input 3 days on task A, week 1, MSP delays task B to start on
week 11
2/ If I input 2 days on task B, week 1, MSP detects a schedule conflict
because it considers that task B starts at the beginning of the week,
despite the fact that the task has a 'as soon as possible' constraint
I seems like MSP spreads efforts over the tracking period, without
considering tasks sequencing...
How to track accurate efforts with MSP, when two tasks are overlapping
during the timescale period (week) ?
Any advice should be appreciated!
Regards
Laurent Breysse
I'm using MS Project Pro 2003, non enterprise version.
We are planning projets by allocating resources up to 80% (time
available for projects, excluding all organizational tasks).
We track efforts (with Actual work and Remaining work) and want a
schedule reflecting the reality.
For understaffing (less efforts produced than planned), updating
actual+remaining work, and rescheduling the planning gives good
results.
For overstaffing (more efforts produced than planned, ex: the engineer
worked 100% of his time on the task), we have to update the Actual work
in the 'Task usage' view to see the planned assignment be updated with
real efforts spent over the week. If not, we do not see the benefits of
a work advance due to an overstaffing.
Here is the problem:
Task A ends Week 1 : Actual work = 3 days
Task B follows task A: Actual work = 2 days
1/ When I input 3 days on task A, week 1, MSP delays task B to start on
week 11
2/ If I input 2 days on task B, week 1, MSP detects a schedule conflict
because it considers that task B starts at the beginning of the week,
despite the fact that the task has a 'as soon as possible' constraint
I seems like MSP spreads efforts over the tracking period, without
considering tasks sequencing...
How to track accurate efforts with MSP, when two tasks are overlapping
during the timescale period (week) ?
Any advice should be appreciated!
Regards
Laurent Breysse