How to View tasks without the outlining?

J

Just Fun

All of my projects have outlined structures that make complete sense to me.
Now my boss wants to see what he calls a "simple list of tasks in order by
date." I have worked with the same layouts for so many years, I don't know
how to accomplish his request.


Any suggestions?
 
M

Manmeet Chaudhari

Create a filter in which you will not be able to see the summary task at all.
Now sort the tasks if essential.
See if this works

Thanks and Regards,
Manmeet Chaudhari
Technical Trainer
Maestros Mediline Systems Ltd
Mumbai
 
M

Mike Glen

Hi Just Fun ,

Welcome to this Microsoft Project newsgroup :)

Tools/Options.../View tab, uncheck the show summary tasks at the bottom of
the dialog. Now Project/Sort.../Start Date. Voila! :)

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 
M

Manmeet Chaudhari

Oh yeah
Thant just dint struck me.
You are great Mike.
Cheers

Manmeet Chaudhari
Technical Trainer
Maestros Mediline Systems Ltd
Mumbai
 
S

Steve House [Project MVP]

FYI - if you still want to see summary tasks but not the indentation, you
can turn the indenting on or off on the same Tools Options View screen.
 