I have several tasks in my planning that must always start on a specific day
of the week e.g. Monday. This is irrespective of which day the predecessor
ends. In other words if the predecessor ends on a Wednesday the next task
must start on the following Monday.
 
J

Jan De Messemaeker

Hi,

Create a new (base) calendar with 1 hour working time in the middle of
Sunday, not a minute more
Create a task with a duration of one hour, assign the Sunday calendar to it.
Make this Sundaty task the successor of the predecessor, and the predecessor
of the successor.
The latter will now start on Monday morning.
HTH
 
J

Jim Aksel

To keep things more clear. Make sure the "1 hour" tasks are the only ones
using the new base calander. Otherwise, Project creates the assumption that
all tasks may perform work on Sunday for 1 hour.

Also, make sure you do not assign any resources or any real work to the
Sunday task, it is just a place holder.

Jan - You are the man! I would never have thought to implement it this way.
No wonder why you are an MVP>
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top