I have a project where I want to assign generic resources for reference only.
I DO NOT WANT TO Resource Load the project. I am having two problems:
1. Project seems insistent on resource-constraining my tasks. I don't care
what resources are assigned, I want my duration to control.
2. When I change calendars for a specific sequence, MSP gets all balled up
in the resource calendar(s). I want a few sequences to be 7/24, and others to
be 5/8. 7/24 ignores holidays and weekends, while 5/8 respects them. I can't
seem to accomplish this objective.
How would you do it?
I DO NOT WANT TO Resource Load the project. I am having two problems:
1. Project seems insistent on resource-constraining my tasks. I don't care
what resources are assigned, I want my duration to control.
2. When I change calendars for a specific sequence, MSP gets all balled up
in the resource calendar(s). I want a few sequences to be 7/24, and others to
be 5/8. 7/24 ignores holidays and weekends, while 5/8 respects them. I can't
seem to accomplish this objective.
How would you do it?