J
John Pollock
In project, I would like to be able to specify that the task should start at
the beginning of the next day (or week or month or hour or whatever).
Due to resource allocations and such, sometimes a task is scheduled to start
in the last hour of a day, where in reality, the work will start the
beginning of the next day.
(As a side note, I often see tasks starting at 5:00 pm - and the calendar
indicates that working time is 8 to 5 - why ??)
In other cases, I want the work to span 5 days without a gap, so the start
time should begin on the following Monday at 8:00 am. While it is possible
to manually add lag time, if the preceeding task moves, the lag time must be
manually adjusted.
Thanks!!!
John
----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.
http://www.microsoft.com/office/com...8075-aa46cf1cffdd&dg=microsoft.public.project
the beginning of the next day (or week or month or hour or whatever).
Due to resource allocations and such, sometimes a task is scheduled to start
in the last hour of a day, where in reality, the work will start the
beginning of the next day.
(As a side note, I often see tasks starting at 5:00 pm - and the calendar
indicates that working time is 8 to 5 - why ??)
In other cases, I want the work to span 5 days without a gap, so the start
time should begin on the following Monday at 8:00 am. While it is possible
to manually add lag time, if the preceeding task moves, the lag time must be
manually adjusted.
Thanks!!!
John
----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.
http://www.microsoft.com/office/com...8075-aa46cf1cffdd&dg=microsoft.public.project