Hello Carolyn,
You're welcome for the assistance. You can use headings or not as you
wish. During the import wizard process (more details below) you will be
able to specify whether the data contains heading rows or not.
Once you have created the comma delimited file, you'll need to import
the resources into a new file or an existing file. If you are importing
into an existing file, open the Project file you wish to import into.
If you are importing into a new file, you'll have that option during
import. Choose File > Open and in the files of type listing select All
Files. Navigate to the comma delimited file you created and choose
Open. The Import Wizard should launch and guide you through the steps
to map the fields from the Notes file into the Project resource fields.
Chances are there will be several pieces of data you may attempt to
import that there is not a direct match to in one of the standard
resource fields. You can always import into one of the text fields
(text1 through text30) to capture additional data from your notes file
that Project doesn't directly use.
I hope this helps. Let us know how you get along.
Julie