G
G. Moore
I'm working how to import Actual Cost by Task from a table in Excel into MSP.
What I'm working towards is an Excel tool to track and summarize project
costs by task, and then be set up to easily pull updated Actual Cost by Task
into MSP. I'm getting nowhere with the Wizard.
I've built a two-field source table in Excel that looks like this (this is
all test data being worked in a sandbox MSP file):
Unique ID Actual Cost
2 $100.00
5 $100.00
6 $100.00
7 $100.00
8 $100.00
9 $100.00
10 $100.00
(etc for 75 or so total records)
I've tried all sorts of paths through the Wizard, none of which work. The
closest I got was with Merging (Prim Key = Unique ID) with Headers a few
lines changed but most did not, and I can't figure out why.
Any suggestions or examples of how this actually works would be appreciated.
Many thanks,
Galen
What I'm working towards is an Excel tool to track and summarize project
costs by task, and then be set up to easily pull updated Actual Cost by Task
into MSP. I'm getting nowhere with the Wizard.
I've built a two-field source table in Excel that looks like this (this is
all test data being worked in a sandbox MSP file):
Unique ID Actual Cost
2 $100.00
5 $100.00
6 $100.00
7 $100.00
8 $100.00
9 $100.00
10 $100.00
(etc for 75 or so total records)
I've tried all sorts of paths through the Wizard, none of which work. The
closest I got was with Merging (Prim Key = Unique ID) with Headers a few
lines changed but most did not, and I can't figure out why.
Any suggestions or examples of how this actually works would be appreciated.
Many thanks,
Galen