Importing/Modifying WBS into Master Project

J

JR

I have two projects and trying to import them. When I do, I get duplicate
WBS codes. Then I tried modifying the subproject WBS but it still imported
duplicate WBS codes. Any ideas?

thanks!

JR
 
J

JulieS

Hi JR,

I am guessing you are inserting project files into a master (not importing?)
and you have the option "Link to Project" enabled. If so, the inserted
subprojects retain their own WBS levels relative to their project. If you
insert the projects without the links, you'll see the WBS numbers change
relative to the master project.

I hope this helps.

Julie
 
J

JR

That did it...Thanks Julie!

JulieS said:
Hi JR,

I am guessing you are inserting project files into a master (not importing?)
and you have the option "Link to Project" enabled. If so, the inserted
subprojects retain their own WBS levels relative to their project. If you
insert the projects without the links, you'll see the WBS numbers change
relative to the master project.

I hope this helps.

Julie
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top