In MS Projects Change Working Time,new button not there wat to do.

J

Jagadeesh B.R

In MS Projects, CHange in working time option, New Button is not present.So
cant able to create New working time..
please help us anybody in this issue.
 
G

Gérard Ducouret

Hello Jagadeesh ,
Aren't you using Project Server ?
If so, by default, that's only the administrator of Project Server who has
permissions to create new calendars
Hope this helps,

Gérard Ducouret
 
M

Mike Glen

Hi Jagadeesh ,

Welcome to this Microsoft Project newsgroup :)

What version of Project are you using and are you up to date with the latest
Service Release?

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 