S
Sherri
I've created a custom cost field that represents the total value of a
deliverable and a second custom cost field that calculates the revenue earned
to date based on the % of work completed. It uses a formula that calculates
[total value]*[%WorkComplete] and is supposed to display the product in the
revenue earned to date field. However, none of the products are accurate
when I do the calculations manually and in most cases are off quite
significantly (thousands of dollars). Is there a reason why this field is not
calculating properly?
example:
Work % Complete = 65%
Total Value = $18,200.00
Revenue earned to date is calculated to be: $4,732.00 (Should be $11830.00)
Thanks for your help.
Sherri
Revenue earned to date should be $1000, but will show up as
deliverable and a second custom cost field that calculates the revenue earned
to date based on the % of work completed. It uses a formula that calculates
[total value]*[%WorkComplete] and is supposed to display the product in the
revenue earned to date field. However, none of the products are accurate
when I do the calculations manually and in most cases are off quite
significantly (thousands of dollars). Is there a reason why this field is not
calculating properly?
example:
Work % Complete = 65%
Total Value = $18,200.00
Revenue earned to date is calculated to be: $4,732.00 (Should be $11830.00)
Thanks for your help.
Sherri
Revenue earned to date should be $1000, but will show up as