P
paul
After searching through the archives for information about %physical
complete, clearly it is an attempt to get around the situation that a
metric based on duration (%Complete) is not always (seldom?) desirable
for earned value calculations. What boggles me is that it seems that
%WorkComplete is the natural choice, but apparently MS disagrees.
Using a painting example by S. House, where the first four days of
work was scheduled for 1 hr/day, with 8 hrs work on day 5.
Duration=5d, Work=12h. At the end of day 4, %WorkComplete=33% and
%Complete=80%. In this situation, it's misleading to take credit
(i.e., the earned value) for 80% of the total cost, but 33% seems
reasonable.
Yet, MS put in this manually entered field of Physical%Complete, which
makes little sense to me. The bricklaying example, with each
successive row requiring more time, clearly illustrates that although
50% of the bricks are laid, more than half of the work and time
remain. Using 50% for the earned value is just silly in this case to
quantify progress against schedule and cost.
So, in the vast majority of cases, IMHO, EV should be based on
%WorkComplete. This is not an option in P2003; has it changed in
P2007? Attempts at using a formula to redefine Physical%Complete have
failed. Is there any way to enable EV calculations within MSP based
on %WorkComplete? Am I off base in my thinking that MS completely
missed the boat on this one?
(The only problem I see is that %WorkComplete can decrease, as
estimates of remaining work are refined. Logically it makes sense to
have less EV then, but it may cause issues when interfacing to
external programs that expect EV to not decrease.)
complete, clearly it is an attempt to get around the situation that a
metric based on duration (%Complete) is not always (seldom?) desirable
for earned value calculations. What boggles me is that it seems that
%WorkComplete is the natural choice, but apparently MS disagrees.
Using a painting example by S. House, where the first four days of
work was scheduled for 1 hr/day, with 8 hrs work on day 5.
Duration=5d, Work=12h. At the end of day 4, %WorkComplete=33% and
%Complete=80%. In this situation, it's misleading to take credit
(i.e., the earned value) for 80% of the total cost, but 33% seems
reasonable.
Yet, MS put in this manually entered field of Physical%Complete, which
makes little sense to me. The bricklaying example, with each
successive row requiring more time, clearly illustrates that although
50% of the bricks are laid, more than half of the work and time
remain. Using 50% for the earned value is just silly in this case to
quantify progress against schedule and cost.
So, in the vast majority of cases, IMHO, EV should be based on
%WorkComplete. This is not an option in P2003; has it changed in
P2007? Attempts at using a formula to redefine Physical%Complete have
failed. Is there any way to enable EV calculations within MSP based
on %WorkComplete? Am I off base in my thinking that MS completely
missed the boat on this one?
(The only problem I see is that %WorkComplete can decrease, as
estimates of remaining work are refined. Logically it makes sense to
have less EV then, but it may cause issues when interfacing to
external programs that expect EV to not decrease.)