Incorrect Values when gennerating Visual Reports

D

Dave

I m trying to generate Earned Value Over Time visual report. Once everything
is exported to excel it doesn't show right data except Actual Costs. Earned
value and Planned value are totally off. They are way more than what they
should be. Please tell me what I m doing wrong.
 
J

JulieS

Dave said:
I m trying to generate Earned Value Over Time visual report. Once
everything
is exported to excel it doesn't show right data except Actual Costs.
Earned
value and Planned value are totally off. They are way more than what
they
should be. Please tell me what I m doing wrong.

Hello Dave,

See the following exchange between another poster and I back in
October about this issue. I haven't had an opportunity to test again
but I hope it may help.

http://groups.google.com/group/micr...d/cca255de4226e4b6?lnk=st&q=#cca255de4226e4b6

I experienced inconsistent results when the Status date was less than
the last tracked data.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 