T
Thomas V
Hi everyone,
I've come across a situation where I'm a little puzzled as to how
resource leveling comes a particular conclusion. It involves Finish to
Finish relationships and constrained tasks
Here are an example of the schedule after Resource Leveling: Leveling
delay on Task3 is set at 11edays.
Name Dur. Constraint Type Start
Finish Res. Predecessor
================================================================
Task1 05 days Start No Earlier Than 17-Dec-07 21-Dec-07 John
Task2 40 days As Soon As Possible 27-Nov-07 21-Jan-08 Mary
Task3 30 days As Soon As Possible 24-Dec-07 01-Feb-08 John 2FF
+2 days
Other relevant info: MSP 2003, Leveling options: Allow Split=yes
I would have expected Automatic leveling to split Task3 such that it
starts as soon as possible while respecting the FF+2 relation to
Task2. What happens though is that Taks3 gets delayed to start only
after Task1 has completed. Seems to me that this breaks the ASAP
constraint.
Interestingly enough, if I inverse the FF relationship such that Task3
is the predecessor then Resource Leveling does split Taks3.
Am I missing something or have I encountered a bug of some sort?
Thanks for the help.
Thomas
I've come across a situation where I'm a little puzzled as to how
resource leveling comes a particular conclusion. It involves Finish to
Finish relationships and constrained tasks
Here are an example of the schedule after Resource Leveling: Leveling
delay on Task3 is set at 11edays.
Name Dur. Constraint Type Start
Finish Res. Predecessor
================================================================
Task1 05 days Start No Earlier Than 17-Dec-07 21-Dec-07 John
Task2 40 days As Soon As Possible 27-Nov-07 21-Jan-08 Mary
Task3 30 days As Soon As Possible 24-Dec-07 01-Feb-08 John 2FF
+2 days
Other relevant info: MSP 2003, Leveling options: Allow Split=yes
I would have expected Automatic leveling to split Task3 such that it
starts as soon as possible while respecting the FF+2 relation to
Task2. What happens though is that Taks3 gets delayed to start only
after Task1 has completed. Seems to me that this breaks the ASAP
constraint.
Interestingly enough, if I inverse the FF relationship such that Task3
is the predecessor then Resource Leveling does split Taks3.
Am I missing something or have I encountered a bug of some sort?
Thanks for the help.
Thomas