I work for a manufacturer. We complete about 30 "jobs" a week. We have a 3
week lead time, so our open order report consistently shows approximately 90
lines. I have exported the open order excel file into project and am
treating each job as a separate task. I want to include the same 8 or 9
steps for each task and want to know if there is a way to accomplish this
without having to cut and paste to each line item 90 times.