M
MorganH
I am trying to set up a master timeline that will show the scheduling of
machine building. The master timeline will be orgainized by the final
product machine being the main tasks, with its sub machines under it. The
problem I am running into are having the need to put the same sub machine
under more then one final product machine. A small sample of the problem is
below:
Machine 1
Sub Machine A
Sub Machine B
Sub Machine C
Machine 2
Sub Machine C
Sub Machine D
Sub Machine E
Both machine 1 and 2 are for the same program, and both have a feeder
machine C. I only need to build one Machine C to feed both main machines.
So as said I want to be able to insert the sub machine into both main
machines, then both main machines into the same master file, when I do so, I
get an error about inserting Sub Machine C in twice (which technically I am).
This master file is not for scheduling, it is to show the total prorgress of
the program, broken down this way to show each main machine and ALL its sub
machines. Any help would be appreciated.
machine building. The master timeline will be orgainized by the final
product machine being the main tasks, with its sub machines under it. The
problem I am running into are having the need to put the same sub machine
under more then one final product machine. A small sample of the problem is
below:
Machine 1
Sub Machine A
Sub Machine B
Sub Machine C
Machine 2
Sub Machine C
Sub Machine D
Sub Machine E
Both machine 1 and 2 are for the same program, and both have a feeder
machine C. I only need to build one Machine C to feed both main machines.
So as said I want to be able to insert the sub machine into both main
machines, then both main machines into the same master file, when I do so, I
get an error about inserting Sub Machine C in twice (which technically I am).
This master file is not for scheduling, it is to show the total prorgress of
the program, broken down this way to show each main machine and ALL its sub
machines. Any help would be appreciated.