Is there a way to only send updated information to someone?

B

Bob

I'm not using a collaboration server and instead of sending the whole plan
around, I'd like to share only the items within the plan that have changed
status. How do I do this?
 
C

Catfish Hunter

If you have set a baseline, set up a filter where Start Variance or Finish
Variance are greater than 0. This will pick up all task not starting on time
or the finish is slipping. Good Luck Bob!!
 
M

Mike Glen

Hi Bob,

Welcome to this Microsoft Project newsgroup :)

You need to identify the information you want displayed in a report
(View/Reports..). You can then print this out and send it to the recipient.
If you want to do this other than by printing, please see FAQ Item: 16.
Project Viewer.

FAQs, companion products and other useful Project information can be seen at
this web address:http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
 