B
Bud
Can you set up separate billing amounts per resource per task in Microsoft
Project?
I would like to designate the rate at which the resource is billed by task.
In other words on one task this resource is billed at $35.00 per hour and on
another task the resource is billed at $50.00 per hour and so on and so on.
This can be 100 different rates for 100 different tasks.
Is there a way to do this? ....and if there is could someone supply a
formula for this such that the end result would appear in the COST field.
There can be many tasks with different rates. The Resource rate area only
allows for 5 if I associate to a resource specific. We need many more than
this.
Project?
I would like to designate the rate at which the resource is billed by task.
In other words on one task this resource is billed at $35.00 per hour and on
another task the resource is billed at $50.00 per hour and so on and so on.
This can be 100 different rates for 100 different tasks.
Is there a way to do this? ....and if there is could someone supply a
formula for this such that the end result would appear in the COST field.
There can be many tasks with different rates. The Resource rate area only
allows for 5 if I associate to a resource specific. We need many more than
this.