keep formatting when importing new data

T

Tomcat

I have formatted a project file a certain way (different colors on gantt bars
and things of this nature). I now want to delete all the current data and
replace it with imported data from Access. When I do this I lose the
formatting. Is there away to keep the formatting. Or can I import data into
an already formatted blank Project file. Thanks.
 
R

Rod Gill

Hi,

Formatting is stored as part of the View and each View when used is copied
to your project file. SO, a fresh import into a new file will have a
different copy of your original view.

However, if you format a view as you want it (and via View, More Views you
can create new ones) you can:

Select Tools, Organizer and copy the views you want to see in all projects
to the Global.Mpt file. Now when you import fresh data into a new file you
will see all views in the Global.Mpt file which will now include the edited
views you copied using the Organizer.
 

Ask a Question