M
MSPuser
Hi,
I have a project that uses a “Spring & Fall Only†calendar with winter and
summer designated as none-working time. The challenge is to keep tasks from
being auto-scheduled to start in spring and finished in the fall.
For example, a 5-day task with the predecessor which finishes on 05/29/06
can be scheduled by MS Project from 05/30/2006 to 09/05/2006. This is not
acceptable, as the task must be completed within 5 calendar days, i.e. it
must be moved to 09/04/06 – 09/08/06.
Putting constraints would not be a good solution as the schedule has
hundreds of dependent tasks and it may require frequent adjustments back and
forward in the future.
Please suggest a way to auto-move the task forward to assure that it would
be always completed within 5 days no matter when the predecessors finishes.
Thank you in advance.
I have a project that uses a “Spring & Fall Only†calendar with winter and
summer designated as none-working time. The challenge is to keep tasks from
being auto-scheduled to start in spring and finished in the fall.
For example, a 5-day task with the predecessor which finishes on 05/29/06
can be scheduled by MS Project from 05/30/2006 to 09/05/2006. This is not
acceptable, as the task must be completed within 5 calendar days, i.e. it
must be moved to 09/04/06 – 09/08/06.
Putting constraints would not be a good solution as the schedule has
hundreds of dependent tasks and it may require frequent adjustments back and
forward in the future.
Please suggest a way to auto-move the task forward to assure that it would
be always completed within 5 days no matter when the predecessors finishes.
Thank you in advance.