Lag time has unexpected length

A

AJennings

Using Project 2003, I need to have a task called Certificate of
Acceptance to come 30 days after Commence System Acceptance Testing.

When I set a 30d value in the Predecessors tab of the Commence System
Acceptance Testing task, the Gantt chart shows the task finishing many
weeks later.

Why is this happening?
 
J

JackD

30 days at 5 days a week (the default for project) is 6 weeks. How many
weeks are you seeing?
 
J

Jim Spiller

The lag you are using is 30 working days. Try using 30ed (for elapsed days)
as the lag.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top