Hello All-
I am having a scheduling issues with MS Project 2007.
My project has the following layout:
- Deliverable 1 task has three subtasks.
- Deliverable 2 task has four sub tasks.
- The duration for each sub tasks is 5 days long.
- I have Fixed Duration set for each task
- The same resource works on all tasks
- There is no dependency between Deliverable 1 and Deliverable 2
When I Level my project MS Project will mix the schedule for tasks from
Deliverable 1 and Deliverable 2. What setting do I have to enable to make
sure that MS project schedules all subtasks for Deliverable 1 together and
all subtasks for Deliverable 2 together? The overall end date does not
change, but from a productivity standpoint it does not make sense for a
resource to mix tasks from one Deliverable with another. Any thoughts?
Thanks in advance.
I am having a scheduling issues with MS Project 2007.
My project has the following layout:
- Deliverable 1 task has three subtasks.
- Deliverable 2 task has four sub tasks.
- The duration for each sub tasks is 5 days long.
- I have Fixed Duration set for each task
- The same resource works on all tasks
- There is no dependency between Deliverable 1 and Deliverable 2
When I Level my project MS Project will mix the schedule for tasks from
Deliverable 1 and Deliverable 2. What setting do I have to enable to make
sure that MS project schedules all subtasks for Deliverable 1 together and
all subtasks for Deliverable 2 together? The overall end date does not
change, but from a productivity standpoint it does not make sense for a
resource to mix tasks from one Deliverable with another. Any thoughts?
Thanks in advance.