Leveling Resources - resource becomes red again

K

Karen

Project 2003
View: Table - Entry

Leveling Resources day by day selected. When it levels the resource for one,
the other one previously fixed becomes red again. What gives?
 
J

JulieS

Hello Karen,

It is likely that you are leveling with the option "Leveling can adjust
individual assignments" enabled. With this option enabled, wen there
are two resoures assigned to a task and both are overallocated, Project
will delay the work for the selected resource without affecting the
other resource. When you try to level the second resource on the task,
Project removes any leveling already done on the task effectively
undoing the earlier leveling.

Try turning the option off.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question