Ben in Property Development
I have two milestones:
1. the lease commencement date
2. the works commencement date
The works commencement date must be not more than 9 months after the lease
commencement date.
Even though the lease commencement date has already happened (4 August 2006)
I want Project to calculate the works commencement date rather than manually
entering it.
Can someone please advise on how to set up the appropriate relationship.
Thank you in anticipation.