Link tasks/milestones that must occur not more than 9 months apart

  • Thread starter Ben in Property Development
  • Start date
B

Ben in Property Development

I have two milestones:

1. the lease commencement date
2. the works commencement date

The works commencement date must be not more than 9 months after the lease
commencement date.

Even though the lease commencement date has already happened (4 August 2006)
I want Project to calculate the works commencement date rather than manually
entering it.

Can someone please advise on how to set up the appropriate relationship.

Thank you in anticipation.
 
G

Gérard Ducouret

Hello Ben,
If the "Lease commencement date" is on the row #10, in the Predecessor
column, in front of the "Works commencement date" which is the successor,
enter the relationship: 10FS+9month.
Nb : This relationship, as all the Project relationships, says that the
successor can't start *before* a lag time of 9 months after the predecessor.
That's not really your "must be not more than 9 months" condition.
Hope this helps,

Gérard Ducouret


"Ben in Property Development"
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top