M
mohmd
Good day gentlemen ;
First of all , it is my pleasure to join pros .
Secondly , I’m an IT user support Admin and I’ve one of th
user facing strange problem with MS prject .
Brief Problem description :
When the user creates new tasks and links them together -> dates o
tasks following the first task won’t change and he has to chang
the dates manually .
I’ve tried playing with some MS project configuration to avoi
some of default settings problem but no luck .
Your help is highly appreciated .
Thanks and once again glad to join pros
First of all , it is my pleasure to join pros .
Secondly , I’m an IT user support Admin and I’ve one of th
user facing strange problem with MS prject .
Brief Problem description :
When the user creates new tasks and links them together -> dates o
tasks following the first task won’t change and he has to chang
the dates manually .
I’ve tried playing with some MS project configuration to avoi
some of default settings problem but no luck .
Your help is highly appreciated .
Thanks and once again glad to join pros