Good day gentlemen ;

First of all , it is my pleasure to join pros .

Secondly , I’m an IT user support Admin and I’ve one of th
user facing strange problem with MS prject .

Brief Problem description :

When the user creates new tasks and links them together -> dates o
tasks following the first task won’t change and he has to chang
the dates manually .

I’ve tried playing with some MS project configuration to avoi
some of default settings problem but no luck .

Your help is highly appreciated .



Thanks and once again glad to join pros
 
J

Jack Dahlgren

Sounds like the calculation settings have changed to manual.
Try hitting the F9 key or go to tools menu/options/calculation tab and set
calculation to automatic.
 
H

Hisham

I agree with Jack. One more thing to check is the [% complete] for the tasks
that need to be linked since tasks with (100% complete) will not change after
linking such tasks. If you still need to change on such tasks then you have
to change the %complete to zero for instance then link the tasks together and
then you can return back the % complete as needed.

Hope this helps

Hisham
http://epmforum.wordpress.com
 
M

mohmd

Thank you pro's for your replies, I asked the user to check such change
and still not get the feedback from him

Whatever the case thank you guys for your replies .

regards.
mohm
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top