R
Rob Stewart
I've created Custom Enterprise task fields and corresponding Custom
Enterprise Project fields, with the intent of showing specific milestone
progress in a PWA Project Center view.
The problem I'm having is linking the two.
I tried importing the formula from the custom task field, without success
I've tried setting a formula in the custom project field which references
the custom Task field. (e.g. [Enterprise Duration2] )
In order to troubleshoot this, in my test project, I've created columns
which represent the custom task fields, and the corresponding custom project
fields. What I'm seeing is that the custom task fields are calculating
properly, but the custom project fields (and assiciated Project Center Views)
are not.
I feel like I'm very close to nailing this down, but have been banging my
head against this for quite some time.
What am I missing?
Thanks,
-RS
Enterprise Project fields, with the intent of showing specific milestone
progress in a PWA Project Center view.
The problem I'm having is linking the two.
I tried importing the formula from the custom task field, without success
I've tried setting a formula in the custom project field which references
the custom Task field. (e.g. [Enterprise Duration2] )
In order to troubleshoot this, in my test project, I've created columns
which represent the custom task fields, and the corresponding custom project
fields. What I'm seeing is that the custom task fields are calculating
properly, but the custom project fields (and assiciated Project Center Views)
are not.
I feel like I'm very close to nailing this down, but have been banging my
head against this for quite some time.
What am I missing?
Thanks,
-RS