K
ko
I'm trying to force one or more task's durations to follow another task. For
example, in a painting project, the surface must first be sanded and then
painted. Obviously, the painting will take at least as long as the sanding.
In a more generic scenario, a project manager will be assigned to a project
for the duration of the project regardless of how long the project lasts. I
would like to be able to link the duration (along with the the start and
finish dates) to automatically track that of the 'master' task.
Has anyone a solution for this?
thanks in advance,
example, in a painting project, the surface must first be sanded and then
painted. Obviously, the painting will take at least as long as the sanding.
In a more generic scenario, a project manager will be assigned to a project
for the duration of the project regardless of how long the project lasts. I
would like to be able to link the duration (along with the the start and
finish dates) to automatically track that of the 'master' task.
Has anyone a solution for this?
thanks in advance,