Hi,
There is the Start to Start link (Task information, Predecessors allows to
select it) which will mostly result in parallel planning. Mostly, of course,
because it only says Task B cannot start before the start of Task A - but
other relationships may cause it to start later.
There is no way in Project to absolutely make sure two tasks are
simultaneous.
HTH