Linking Work column to start and finish dates

S

Steve

I've set up a plan and copied a portion of another plan into it. The
upper portion of the plan has the work (person-hours) driving the start
and finish dates. However, in the bottom portion of the plan these do
not link and if I put in 25 hours for a task the dates do not change.
Wondering how to correct this problem.

Thanks in advance for any insight into the issue.

Steve Hilton
 
J

Jan De Messemaeker

Hi Steve,

I must admit I don't understand much bout upper and lower part of the plan.
Just to make sure, in Tools, Options, Calculation, is calculation set to
automatic?
HTH
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top