LOE Threshold

W

Waddle

Are there any guidelines or standards that speak to limiting LOE tasks when
developing a schedule? Is there a threshold for LOE tasks in the schedule?
 
J

John

Waddle said:
Are there any guidelines or standards that speak to limiting LOE tasks when
developing a schedule? Is there a threshold for LOE tasks in the schedule?

Waddle,
Normally this is dictated by contract or corporate policy. For lack of
any other criteria, LOE should be a very small percentage (e.g. 5-10%)
of the whole project, otherwise you are not going to have very accurate
planning and/or tracking.

John
Project MVP
 
J

Jim Aksel

Our customer allows 20%. However, our internal policy allows 0%. LOE is
always tracked in a separate schedule. The two schedules are combined into a
master project for reporting purposes. Internally we manage to the measured
schedule.
--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Similar Threads

Looking for a metrics reporting tool. 1
Looking for a metrics reporting tool. 0
LOE Plan Hours 1
Leveling LOE Tasks 13
2007 & LOE work 4
LOE Question 1
2007 actuals 2
Contoured Level of Effort 5

Top