M
Michael Zenner
This is one of those 'set once and it is forgotten'. Well, I forgot, and need
to have, after a hard drive crash.
I use Project to import a text file, that is the previous night's activity
on our mainframe computer. I am monitoring for specific jobs and critical
paths each morning, week, and month, for problems, and Project works well for
me, with it's filters.
The import file, tab delimited, and contains:
* ID
* Name
* Text1
* Note
* Start (date and time)
* Finish (date and time)
* Duration (in minutes, and identified with "MINS")
* % Complete
* Predecessor
* Date1
Set my calendar option to default start and end times to "0:00", my hours in
a day to 24, 168 hours in a week, and 20 days in a month. I have my date
display for date and time, and Windows 2K is set to have a 24 hour clock
display.
I used to import the file, then set to 24 calender, and everything was fine.
Now, I import, and the Finish is recalculated to the elapsed and 8 AM, if
the task runs after 5 PM. So I job that started at 7 AM, ran 1 minute of
Duration, has a Finish of 8:01 AM, instead of the 7:01 AM the file has.
I know there is some option that I am missing, and as soon as someone tells
me, I will slap my forehead and say "Yes, that is it".
Thank you in advance for your help,
Michael Zenner
to have, after a hard drive crash.
I use Project to import a text file, that is the previous night's activity
on our mainframe computer. I am monitoring for specific jobs and critical
paths each morning, week, and month, for problems, and Project works well for
me, with it's filters.
The import file, tab delimited, and contains:
* ID
* Name
* Text1
* Note
* Start (date and time)
* Finish (date and time)
* Duration (in minutes, and identified with "MINS")
* % Complete
* Predecessor
* Date1
Set my calendar option to default start and end times to "0:00", my hours in
a day to 24, 168 hours in a week, and 20 days in a month. I have my date
display for date and time, and Windows 2K is set to have a 24 hour clock
display.
I used to import the file, then set to 24 calender, and everything was fine.
Now, I import, and the Finish is recalculated to the elapsed and 8 AM, if
the task runs after 5 PM. So I job that started at 7 AM, ran 1 minute of
Duration, has a Finish of 8:01 AM, instead of the 7:01 AM the file has.
I know there is some option that I am missing, and as soon as someone tells
me, I will slap my forehead and say "Yes, that is it".
Thank you in advance for your help,
Michael Zenner