A
Alexandra
Hello,
I have tasks X, Y and Z.
X takes 2 estimated days (from day 1 to day 2) and Y takes 3 estimated dates
(from day 1 do tay 3).
Then I want to make task Z depend on those two tasks, in a way that it
starts when as soon as the one of them finishes, but if I do one simple FS
dependency, it will start on day 3 because it starts on the day that the
longest task finishes. Is there anyway to make it start on the day the
shortest task finishes?
Make it an OR dependency instead of a AND ?...
Thank you
I have tasks X, Y and Z.
X takes 2 estimated days (from day 1 to day 2) and Y takes 3 estimated dates
(from day 1 do tay 3).
Then I want to make task Z depend on those two tasks, in a way that it
starts when as soon as the one of them finishes, but if I do one simple FS
dependency, it will start on day 3 because it starts on the day that the
longest task finishes. Is there anyway to make it start on the day the
shortest task finishes?
Make it an OR dependency instead of a AND ?...
Thank you