Making a report for activities by end date and list activities onc

K

Karl 79

Hi!

I have a project plan that I want to present to the project group in the
following way:

The report should present all activities that are not completed, sorted by
weeks and all activities should only be shown in the same week as they are
supposed to be finished.

My problem when making my report is that all activities are shown every week
they are "active". The report is therefore a lot longer than I want it to be.

I guess I need to make a filter of some kind, but I'm kinda stuck at the
moment.

Anyone with a good answer?

Thanx in advance :)
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top