Sebastian Cordoba
Hi everyone.
I have this situation: I manually modify the baseline duration for a task. I
did it "accidentally" because I didn't know I could do that. After that I
made some changes and then saved the project.
The problem now is that I'm not sure about the original baseline duration.
How do I recover it? How to prevent user from doing this? 'Til today I
thought that baseline values couldn't be modified.
Thanks.