S
Seann
I have two resources in my project file that are marked Bold/Red in the
resource usage page, indicating overallocation.
As I scroll through the dates, the days that are marked red are actually
days in the past. The resources were scheduled at 6.8hrs (85%) on those days,
yet the actual work they applied to their tasks was 5.5 and 5 respectively. I
don't understand why project would mark these (RED) as overallocated when
they don't appear to be.
We have leveled the project with no effect to these two days.
resource usage page, indicating overallocation.
As I scroll through the dates, the days that are marked red are actually
days in the past. The resources were scheduled at 6.8hrs (85%) on those days,
yet the actual work they applied to their tasks was 5.5 and 5 respectively. I
don't understand why project would mark these (RED) as overallocated when
they don't appear to be.
We have leveled the project with no effect to these two days.