Master and Subprojects in EPM

T

Tameem

Hi

I created 5 projects in MS project 2003 Professional 2003 . this
projects was saved on the EPM server. i created a Master and inserted
all this 5 projects. But the duration got changed and some task
duration got doubled where by giving a difference.

I did the same activity in my local PC i did not have problems of task
duration.

How can i get solve this ?
Kindly provide your valuable help

Regards
Tameem
 
G

Gary L. Chefetz [MVP]

Tameem:

This sounds like calendar differences causing the change. Your local base
calendar and your Enterprise base calendars may not be the same.
 