"Master Project" How to seamlessly have two projects be one...?

J

JPD

I am working with our headquarters on a schedule where 50% of the work
is here at my location and the other 50% of the work is being done at
our headquarters. I have been brought on to help with managing the
schedule "after the fact" in other words its already planned out with
resources, tasks, etc.

The line between the two sets of work is pretty clear and ideally I
would like to manage my part completely separate. The powers that be
at headquarters are against it. So I am trying to figure a way that I
can essentially manage my part of the work and then integrate it back
into the "Master Project". I need to provide my program manager here
with resource analysis, EVM exports, etc etc.

Any ideas how to best do this?
 
J

Jan De Messemaeker

Hi,

It's a long story but it can indeed be done "seamlessly"
You could start looking for the help on
Insert Project
and
Resource Sharing

Feel free to come back with more detailed questions as they arrive!
 