I am using Project 2003 Standard. I have created a Master Project (Portfolio)
based on a shared Resource Calendar.

I am trying to display a Resource Usage report filtered for an individual
project in the portfolio or create a view that summarizes resources by
project. The problem I am having is that when I filter by a specific project
the resource summary lines still contains the total for the resource across
all projects in the Master.

Any suggestions or examples of how I can correct this?
 
R

Rod Gill

Have you tried Grouping by the Project Field? Groups are from the Project
menu. Create a new Project Group
 
S

Steve Wade

I tried your suggestion Rod but when I group by project I now get a summary
line at the top orf the resource usage report that is labelled with the
title of my resource calendar.
 