J
Jerryinnc
I have created a master project with links to 2 projects.
When I look at the resource usage in the master project it shows the 2
projects and the work associated with each project - one line per linked
project.
If I go into either of the 2 linked projects and add/change/delete a task
and then go to the master project I no longer see a summary line for the
project that I added/chanegd/deleted the task, but see all tasks from that
linked project for that resource. How do I keep the summary level resource
usage for the project that has been adde/changed/deleted tasks and not see
all tasks?
When I look at the resource usage in the master project it shows the 2
projects and the work associated with each project - one line per linked
project.
If I go into either of the 2 linked projects and add/change/delete a task
and then go to the master project I no longer see a summary line for the
project that I added/chanegd/deleted the task, but see all tasks from that
linked project for that resource. How do I keep the summary level resource
usage for the project that has been adde/changed/deleted tasks and not see
all tasks?