KK said:
I have created a resource and its type is Material and the material label is
Dollars. However, when I run a Resource Usage (material) report in Project
2000 some, and I emphasize some not all, of the tasks using that resource say
1500hrs instead of 1500.
How can I fix this.
Regards
KK
KK,
OK well that's a strange one. Here are a few things to try/consider.
First, do you have the SR-1 update installed? If not, install it.
Second, try running Detect and Repair from the Help menu.
Does this happen with just one isolated file or multiple files? If it's
just one file you might have corruption. Go to our MVP website at:
http://www.mvps.org/project/faqs.htm
and take a look at FAQ 43 - File Bloat? Might be corruption.
Is the file tied to a common resource pool? If so, there could be a
conflict with a resource name that is of material type in one place and
the same resource name that is of work type in another place.
Create a new resource of work type and substitute it for one of the
assignments that demonstrates the problem. It should show "hours" in the
Usage view. Then create a new resource of material type and substitute
that for the same assignment. What happens?
Hopefully one of these suggestions will help. If not, I may need to look
at the file itself.
John
Project MVP