Micosoft Project 2007 - Visual Reports

P

PS

Hi

Is there any way to change the chart exported for earned value over time
from years and quarters to calendar dates? If so, how can this be done?

Thanks.
 
J

JulieS

Hello PS,

The information in the chart is from the excel pivot table. If you
expand the quarters and weeks it shows days. You need to make sure
you specify the appropriate measurement when you create the cube. You
can modify the chart by modifying the pivot table.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
P

PS

Hi Julie,

Thanks for your reply - I am aware that if I select days in the view reports
dialog box and expand the pivot table I can see days but what I actually want
to do is be able to select weeks in the view reports dialog box and see the
first calendar date of the week for each week on the chart (like in MS
Project 2003 with the analyzed time scale data function).

Is there a way I can do that without having to select days in the view
reports dialog box?
 
J

JulieS

Hello PS,

To the best of my knowledge, no. The date format in the Excel pivot
table seems to be generated in some semi-mysterious way. I've yet to
figure out exactly where it is getting the labels from -- it isn't the
week number of the year nor week number of the project (from start).
The only method I know of is to manually enter the data you wish to
see in the pivot table.