MS Project 2007 - Earned Value over Time Report

P

PS

Hello,

I ran the earned value over time visual report in MS Project 2007 for a
schedule. The pivot table that is exported has year and quarter in bold from
the time weekly calendar in the field pick list because these are in the
pivot table. Is there a way to change the field pick list and pivot table
such that the timelines shown in the pivot table are not year and quarter but
calendar dates?

Thanks.
 
D

Dale Howard [MVP]

PS --

No, you are restricted to the time periods specified in the Visual Reports
dialog and in the resulting Excel PivotTable. Hope this helps.
 
P

PS

Hello,

Is there some way at all to change the time period to calendar dates in
excel maybe from the extracted pivot table? Or is there some conversion from
these quarters and weeks to calendar dates or to iso weeks (week numbers)? I
know there is a conversion from calendar dates to iso weeks in excel. I want
to modify from these quarters and weeks to calendar dates on the chart.

Thanks.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top