Why would progress not show for certain line items within a project?
It worked in the past and for whatever reason it will not work now.
 
S

salgud

Why would progress not show for certain line items within a project?
It worked in the past and for whatever reason it will not work now.

You need to give more detail. Have you tracked/entered progress? If so,
how?
 
B

B Sai Prasad [PMP]

Dear Angelica -

I hope you are taking about incorrect progress displayed by progress lines /
status field.

If I am correct, then check the Status Date in Project, Project Information
dialog box. Status field uses Status Date to calculate the progress. If you
are using Progress lines, then may be have set the progress line to be drawn
w.r.t. to status date.

Info: If Status Date in Proj Information dialog box is NA, the Status Date
is equated to Current Date field.

If my suggestion helps, please consider rating my reply.
 