D
Doc
Has anyone developed a Week-ending report for Microsoft Project?
Currently all of the timescale "timephased" data are based on
Week-starting. What I am looking for is someone who has developed a
macro, custom report, or mapped the internal data to a spreadsheet to
create a week-ending report. For example the first week in October end
on Saturday:
Sun Mon Tue Wed Thu Fri Sat
25 26 27 28 29 30 1 <-- Week ending Nov 1
Microsoft project Resource Usasge report with a two-tiered timescale
would put this week into the October "bucket" as the week starts Sep
the 25th;
9/25-10/01
Regards
Doc
Currently all of the timescale "timephased" data are based on
Week-starting. What I am looking for is someone who has developed a
macro, custom report, or mapped the internal data to a spreadsheet to
create a week-ending report. For example the first week in October end
on Saturday:
Sun Mon Tue Wed Thu Fri Sat
25 26 27 28 29 30 1 <-- Week ending Nov 1
Microsoft project Resource Usasge report with a two-tiered timescale
would put this week into the October "bucket" as the week starts Sep
the 25th;
9/25-10/01
Regards
Doc