etc.
Milestones in Project should be used for two things. They can be used to
mark the start of a group of tasks and they can be used to mark the
completion of a group of tasks. Milestones should NOT be linked to other
milestones - it serves no purpose. The most prevalent use of a milestone
is to mark the completion of a significant group of tasks within an
overall project plan (i.e. preliminary design review, completion of the
slab for a house, etc.). The milestone "floats" based on how the driving
tasks are performing. Although a milestone may be roughly related to a
previous milestone, it is dependent on the tasks that lead up to it and
not the previous milestone itself.
Perhaps what you really want is a series of deadlines. For that you
should use the Deadline field. Basically you set the date and Project
puts a deadline marker on the Gantt Chart display. You can read more
about the Deadline field in the Project help file.
By the way, the answer to your question is yes, but it is a misuse of
the milestone concept. If you really really want to chain milestones,
just put a lag in the link between them.
John
Project MVP
I'm going to have to respectfully disagree with John. The two uses he
suggests for milestones are some of the major uses, but there are others.
Examples would be any Go-No Go decision on the project, the release of a
major report or other document (like scoping document), major project
reviews or control points. An example of the last is one I learned in a PM
class and used for many years on medium to large mining and oil
construction projects. I was taught that civil work should begin by the
time design work was 10% complete, which was not an easy thing to make
happen. But it helped to insure a good start on these kinds of projects. So
I always inserted a milestone, for me and my team, showing the point at
which the Design Phase was 10% complete. Then I'd try to make sure that all
of the tasks that needed to happen in order for the civil work to start
finished by that same time. Of course, I couldn't just link from the 10% Ms
because that would have been artificially forcing the start of Civil work,
possibly before the necessary predecessors were complete.
I believe in using milestones wherever you feel you need a marker in your
schedule. Of course, I don't advocate peppering your project with them and
diluting their value.
Hope this helps in your world.