Rhonda H
I have a MS Project Plan that is made up of summary level
and milestones (see below). I am updating the %complete
for each milestone as it is done. I also use the Status
field in a view to report status to management. The
problem is at the Summary level (tasks) the status field
shows "Late" and the %complete is zero although the
milestones below are not late (see below).
Task Name Status %cmpl Start Finish
Summary One Late 0 02/12/04 02/20/04
Miles 1 Complete 100 02/12/04 02/12/04
Miles 2 Complete 100 02/14/04 02/14/04
Miles 3 Future Task 0 02/20/04 02/20/04
I would think that the summary level would at least show a
status of "On Schedule". Any ideas? Does anyone know how
the status is determined for a milestone and for tasks
with no work effort?
Thanks in advance,
Rhonda
and milestones (see below). I am updating the %complete
for each milestone as it is done. I also use the Status
field in a view to report status to management. The
problem is at the Summary level (tasks) the status field
shows "Late" and the %complete is zero although the
milestones below are not late (see below).
Task Name Status %cmpl Start Finish
Summary One Late 0 02/12/04 02/20/04
Miles 1 Complete 100 02/12/04 02/12/04
Miles 2 Complete 100 02/14/04 02/14/04
Miles 3 Future Task 0 02/20/04 02/20/04
I would think that the summary level would at least show a
status of "On Schedule". Any ideas? Does anyone know how
the status is determined for a milestone and for tasks
with no work effort?
Thanks in advance,
Rhonda