H
Henrik Jensen
The case
Task A has a finish-to-start relationship to Task B
Task A starts on january 1., duration 2 days, assignment = Resource 1
Task B, duration 5 days, assignment = Resource 2
The problem
I can't figure out why the critical path dissapears when a resource,
assigned to Task B, have a nonworking day on january 3.
If the resource have a nonworking day on january 4. the critical path exists.
Please help med understand!
Task A has a finish-to-start relationship to Task B
Task A starts on january 1., duration 2 days, assignment = Resource 1
Task B, duration 5 days, assignment = Resource 2
The problem
I can't figure out why the critical path dissapears when a resource,
assigned to Task B, have a nonworking day on january 3.
If the resource have a nonworking day on january 4. the critical path exists.
Please help med understand!