M
Mark E
Hi.
I have a problem which I fear may be out of Project's capability to solve
and wondered if anyone out there may know different?
If I define a task as being of a specific duration (effort) and want to
model the effects on project duration by adding worker resources. If we say
a skilled worker has an efficiency of 1 and a trainee worker has an
efficiency of 0.75, this would mean that the trainee has the capacity to
produce 75% of the work of a skilled worker in the same time.
I would like to model the effect of varying the ratio of skilled/trainee
resources employed on the task but so far have been unable to find a way of
modelling their relative productivity. I would have thought that this would
be a powerful feature to have within the application and would be mildly
surprised if indeed it is not possible.
Many thanks in anticipation of your kind comments.
I have a problem which I fear may be out of Project's capability to solve
and wondered if anyone out there may know different?
If I define a task as being of a specific duration (effort) and want to
model the effects on project duration by adding worker resources. If we say
a skilled worker has an efficiency of 1 and a trainee worker has an
efficiency of 0.75, this would mean that the trainee has the capacity to
produce 75% of the work of a skilled worker in the same time.
I would like to model the effect of varying the ratio of skilled/trainee
resources employed on the task but so far have been unable to find a way of
modelling their relative productivity. I would have thought that this would
be a powerful feature to have within the application and would be mildly
surprised if indeed it is not possible.
Many thanks in anticipation of your kind comments.