Monthly cost allocation to tasks

M

Mark N

I'd like to associate monthly cost associated with each task based on the
duration of the task. Each month may have a different value based on monthly
work performed.Then i would like a monthly cost summary.
Is this possible?
Thanks in advance
Mark N
 
J

John

Mark N said:
I'd like to associate monthly cost associated with each task based on the
duration of the task. Each month may have a different value based on monthly
work performed.Then i would like a monthly cost summary.
Is this possible?
Thanks in advance
Mark N

Mark,
Unless I'm missing something, you can simply use the Task Usage view set
up with a monthly timescale.

John